Alan Baxter and Associates were
structural engineers for the Royal Opera House
development for over ten years. They were eventually
replaced during the troubles that surrounded the project
but in my time I was associated with the following works:-
- Design of the
Fly Tower
- Refurbishment
of the Phase 1 building to allow relocation of
businesses from Russell Street into James Street
- Construction
of temporary Accomodation inside the Floral Hall
to provide changing areas for artists displaced
from the Phase 1 building.
 The Fly tower was to be a monumental
structure over an even more monumental basement. The
latter to accomodate new set building areas and lifts to
bring the completed sets up to the stage. Four concrete
legs containing stairs and access lifts provided support
for trusses supporting the roof, stage equipment and wall
cladding. Unfortunately this element of the works necver
came to fruition under ABA.
The Phase 1
accomodation works and the temporary accomodation in the
Floral Hall were more successful. The former involved
forming openings for stairs to convert the old changing
rooms into a two level bar/ restaraunt, and filling in
old unwanted voids. The biggest challenge was trying to
dissuade the tennant's designers from requiring us to dig
up most of the heavily reinforced piled basement slab in
order to re-arrange the drainage.
The temporary
accomodation inside the Floral Hall was a major structure
in itself, being 3 storeys high in composite steel. We
also had to prove the existing jack arch slab and its
cast iron supporting beams. This we did by a combination
of analysis and a historical study of its previous use.
|