Week 14

2nd July 2001

Ceiling joists can now go down.
1st course of the gable is built at 1 end.

Tuesday and more floor joists in place.
The other gable end is built up.
After 50 dustbin bags of ceiling plaster and paper we get a skip for the wall plaster.

By Wednesday the gables are complete

Timbers are cut ready for bringing down at the front.  Notice the space left for the dormer.

Thursday and floor joist are ready for the front timber construction.

Friday and front timber construction is set out.

The first of the old timber floor is fully removed with hardcore now starting to go in.

Internal walls are starting to come down.

Saturday and old lounge door openeing is bricked up, you just can't get the staff.

Dividing wall between old bedroom and study is down.
Front window is removed to be replaced be the front doorway/porch.

Sunday and fireplace is re-opened out.

Hall way wall is now down so we thought we better support the beam as it was only sitting on 2 bricks.