Week 14
2nd July 2001
|
Ceiling joists can now go down. |
| 1st course of the gable is built at 1 end. |
|
|
Tuesday and more floor joists in place. |
| The other gable end is built up. |
|
|
After 50 dustbin bags of ceiling plaster and paper we get a skip for the wall plaster. |
| By Wednesday the gables are complete |
|
|
|
Timbers are cut ready for bringing down at the front. Notice the space left for the dormer. |
| Thursday and floor joist are ready for the front timber construction. |
|
|
|
Friday and front timber construction is set out. |
|
The first of the old timber floor is fully removed with hardcore now starting to go in. |
|
|
|
Internal walls are starting to come down. |
| Saturday and old lounge door openeing is bricked up, you just can't get the staff. |
|
|
|
Dividing wall between old bedroom and study is down. |
| Front window is removed to be replaced be the front doorway/porch. |
|
|
Sunday and fireplace is re-opened out. |
![]() |
|
|
Hall way wall is now down so we thought we better support the beam as it was only sitting on 2 bricks. |