Week 16
16 July 2001
|
|
Monday Plywood on the side of the front bedroom and all the timbers for the front of the roof in place. |
| Skip number 2 is now full and needs to go back. |
|
|
Tuesday and 2 tonne of gravel is delivered. It turned out we only needed 1 quarter of that. Never mind it will get used in the drains.
|
|
|
|
Sewer pipes down in place. |
| Wednesday and dormer has got it's round window space. |
|
|
|
Timber is ready for the roof at the gables. |
|
Thursday and it is raining and the roofers turn up. |
|
|
|
Sunfold patio door is delivered. |
| Friday herringbone strutting between 1st floor joists. |
|
|
|
Roofers round again because it looked like rain. |
|
|
Saturday and the bedrooms 1 and 2 have flooring down. I can't believe how long it took me to do this. |
|
exposed timber has it's first coat of stain. |
|
|
Sunday and bedroom 3 has part of it's floor down. |
![]() |
|
|
The baby pigeons are almost ready to leave their home in the temporary roof. |