Week 16

16 July 2001

Monday Plywood on the side of the front bedroom and all the timbers for the front of the roof in place.
Skip number 2 is now full and needs to go back.

Tuesday and 2 tonne of gravel is delivered.  It turned out we only needed 1 quarter of that.  Never mind it will get used in the drains.

 

Sewer pipes down in place.

Wednesday and dormer has got it's round window space.

Timber is ready for the roof at the gables.

Thursday and it is raining and the roofers turn up.

Sunfold patio door is delivered.

Friday herringbone strutting between 1st floor joists.

Roofers round again because it looked like rain.

Saturday and the bedrooms 1 and 2 have flooring down.  I can't believe how long it took me to do this.

exposed timber has it's first coat of stain.


Sunday and bedroom 3 has part of it's floor down.

The baby pigeons are almost ready to leave their home in the temporary roof.

 