Week 17

23 July 2001

Monday and a busy day.  The building inspector came around to see the waste pipes but didn't find any problems.  And the underfloor heating system was delivered.

Kitchen wall was knocked down so we could see the floor levels

Tuesday still recycling the old bricks until the bought in MOT hardcore arrived.
Hardcore wackered down and nice and smooth.

Wednesday and with the hardcore nice and smooth we start to lay the Radon / damproof membrane over.
By end of play we had a pile of hardcore left over to match the existing pile of gravel.

Thursday and the old holes left by the floor joists needed filling.

By Friday, the membrane was almost fully down and just needed attaching to the walls with bitchumen tar and a few nails.

Friday was pretty hectic with the building inspector coming in the afternoon and I had to pick up 3 wheelbarrows and shovels and a rake for the following day's concreting.

The building inspector had a gook look around and basically OK'd everything he saw.


Saturday morning and 7:30 the first load of concrete arrived. 4 and a half cubic metres
Starting to go down.
a quick breather before the second load arrived at 10:30.  3 cubic metres this time as I got a bit twitchy and increased the order by half
Needless to say we had plenty left over.  About half a cubic meter at a guess.
After cutting away the covering for the temporary roof the left over was spread at the back underneath where the veranda will be.

Sunday we didn't/couldn't do anything.


Back to timeline.