Week 18

30 July 2001

Monday and inner wall in entrance area is built up to support the RSJ.
The front doorway is starting to be bricked up.

Tuesday and the remaining flooring upstairs is starting to be laid.
At last we can walk around safely.

Wednesday and the front opening is squared off.

small window from the side is now in at the front.

Friday and the internal studwork is started.

All the doors and window arrive

Saturday and the 2 bathroom windows are in.

Sunday and the front window is in
Along with Coral's bedroom window

Back to timeline.