Week 20
13th August 2001
This week is the big push to get ready for plastering the following week.
|
|
The electrics I ordered arrived and I made a start.
The first back box goes on the wall. |
| Tuesday and the RSJ is battened ready for plasterboard. |
|
More electrics in the evening.
|
|
Wednesday and the start of the finishing off jobs.
Loft hatch. |
|
Window Cills. |
|
More electrics in the evening.
|
|
Thursday and modifications were made to the roof at the front to bring it down further. |
More electrics in the evening.
| Saturday and the focus was on the upstairs lighting circuits. |
|
|
|
Digger and dumper arrived for the following Monday. |
|
Sunday and the electrics upstairs are 95% finished so I should get them all done by next Friday when the people come to dry line the walls. |
|