Week 20

13th August 2001

This week is the big push to get ready for plastering the following week.

The electrics I ordered arrived and I made a start.

The first back box goes on the wall.


Tuesday and the RSJ is battened ready for plasterboard.

More electrics in the evening.


Wednesday and the start of the finishing off jobs.

Loft hatch.

Window Cills.

More electrics in the evening.


Thursday and modifications were made to the roof at the front to bring it down further.

More electrics in the evening.


Saturday and the focus was on the upstairs lighting circuits.

Digger and dumper arrived for the following Monday.

Sunday and the electrics upstairs are 95% finished so I should get them all done by next Friday when the people come to dry line the walls.