Week 29

15 Oct 2001

The plumber was going to work evenings this week so we had water upstairs

Monday and Tuesday came and went but no sign of him.

By Wednesday the garage has been built up.

And the utility at the back.

The electricity and gas meters were supposed to be installed.

The electric was but the gas people would not work underneath the scaffold.

Still no sign of the plumber.


Thursday and the concrete arrived for the base of the porch and the rear utility

It sunk into the hardcore of the garage floor and  had to empty it's load before it could move off.

By the end of play the utility slab was down.

Still no plumber though.


Saturday and we made a start on the under-floor heating upstairs.

No sign of any plumber though.


Sunday was a lazy day and it was decided that the plumber had to go.


Back to timeline.