Week 5

30/Apr/2001

It's going to be a short week this week.  Not because of the lack of progress but due to the fact we went away on Thursday night so I couldn't fully capture the progress.  Normal service will be resumed on Tuesday of week 6.

But for now...


Monday and the walls get Higher and Higher.

First floor joists are cut to length.

Tuesday and the Joists are now in place.

Tuesday night and I get home from playing 5 a side football to make profiles again in the dark.


Wednesday and the end of this weeks coverage of the extension.  No builders on Thursday and we are away Thursday night.

The walls are getting higher and my profiles are put in place.


Back to timeline.